According to the latest Progress Report email we are 12% complete on the build. The drains have been completed and connected to the main sewer, the sand around the perimeter of the slab has been levelled, site power has been connected, a materials storage shed has been put on site and the window frames have been delivered. We are just waiting on the bricks which are scheduled for delivery on Monday and we will start to see the bricklayer do some magic.