Tuesday, September 21, 2010

Looking Through The Windows

Today the windows went in and it was a thrill to look out of glass rather than open spaces. We don't have long to go now Yippee!




Rendering

One step closer to the finished product and it's looking great!




Digging Trenches

When we were quoted $600 for a trench to be dug for the telephone lines, Trevor whipped out the shovel and did it himself with an extra hand from Riley saving us some money, thanks Trevor.




Friday, September 3, 2010

The Roof!

On Wednesday there was no roof only the timber, Thursday it looked like this. They must have had a big team there or work really fast as it was done in 1 day! It really is looking great and not too long now until we have our house back.










Saturday, August 28, 2010

48% Complete

We are almost half way there! The roof frame is complete and the plumbing, gas and electrical has been installed in the roof and chased into the walls. The gutters have been delivered on site and soon the roof cover for the roof will be and then the roof will be completed.









Sunday, August 15, 2010

Trevor's Photos

Today we took my folks to see the house and Trevor took some photos to take to his folks (we were having lunch there) so they could see what has been done since they saw the pad. Some of them are from different angles than I have taken so I thought I would post them on here.










Saturday, August 14, 2010

Gables

We loved turning up and seeing the gabels, it is looking better and better every visit.